New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 134 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 134 Topic 14 Discussion

CAPM Exam Topic 14 Question 134 Discussion:
Question #: 134
Topic #: 14

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?


A.

Estimate at completion


B.

Cost performance


C.

Schedule performance


D.

To-complete performance


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.