PMI Certified Associate in Project Management (CAPM) CAPM Question # 134 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 134 Topic 14 Discussion

CAPM Exam Topic 14 Question 134 Discussion:
Question #: 134
Topic #: 14

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000


A.

1


B.

0.4


C.

0.5


D.

0.8


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.