Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 116 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 116 Topic 12 Discussion

CAPM Exam Topic 12 Question 116 Discussion:
Question #: 116
Topic #: 12

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:


A.

start-to-start (SS)


B.

start-to-finish (SF)


C.

finish-to-start (FS)


D.

finish-to-finish (FF)


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.