Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 116 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 116 Topic 12 Discussion

CAPM Exam Topic 12 Question 116 Discussion:
Question #: 116
Topic #: 12

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?


A.

Informal communication


B.

Internal communication


C.

Formal communication


D.

Horizontal communication


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.