Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 116 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 116 Topic 12 Discussion

CAPM Exam Topic 12 Question 116 Discussion:
Question #: 116
Topic #: 12

The following is a network diagram for a project.

CAPM Question 116

The shortest non-critical path for the project is how many days in duration?


A.

10


B.

12


C.

14


D.

16


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.