Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 208 Topic 21 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 208 Topic 21 Discussion

CAPM Exam Topic 21 Question 208 Discussion:
Question #: 208
Topic #: 21

A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?


A.

Early requirements gathering


B.

Feedback analysis


C.

Progressive elaboration


D.

Requirements documentation


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.