New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 207 Topic 21 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 207 Topic 21 Discussion

CAPM Exam Topic 21 Question 207 Discussion:
Question #: 207
Topic #: 21

How is the schedule variance calculated using the earned value technique?


A.

EV less AC


B.

AC less PV


C.

EV less PV


D.

AC less EV


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.