New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 209 Topic 21 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 209 Topic 21 Discussion

CAPM Exam Topic 21 Question 209 Discussion:
Question #: 209
Topic #: 21

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?


A.

Cost-reimbursable contracts


B.

Time and Material contracts (T&M)


C.

Fixed-price contracts


D.

Cost Plus Fixed Fee Contracts (CPFF)


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.