PMI Certified Associate in Project Management (CAPM) CAPM Question # 377 Topic 38 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 377 Topic 38 Discussion

CAPM Exam Topic 38 Question 377 Discussion:
Question #: 377
Topic #: 38

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?


A.

If the operation team members were trained externally


B.

If the transition process was agreed upon during the build


C.

If the end-user documentation was more thorough


D.

If the operations manager was invited to all sprint reviews


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.