PMI Certified Associate in Project Management (CAPM) CAPM Question # 103 Topic 11 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 103 Topic 11 Discussion

CAPM Exam Topic 11 Question 103 Discussion:
Question #: 103
Topic #: 11

What process in Project Schedule Management identifies and documents specific actions to be performed to produce a project’s deliverables?


A.

Plan Schedule Management


B.

Define Activities


C.

Develop Schedule


D.

Estimate Activity Durations


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.