PMI Certified Associate in Project Management (CAPM) CAPM Question # 101 Topic 11 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 101 Topic 11 Discussion

CAPM Exam Topic 11 Question 101 Discussion:
Question #: 101
Topic #: 11

A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client's project manager. The technical lead is requesting two new developers.

Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?


A.

Cost management plan


B.

Business management plan


C.

Stakeholder engagement plan


D.

Resource management plan


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.