PMI Certified Associate in Project Management (CAPM) CAPM Question # 99 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 99 Topic 10 Discussion

CAPM Exam Topic 10 Question 99 Discussion:
Question #: 99
Topic #: 10

A business analyst needs to ensure the project team understands the most critical roles and responsibilities within the requirements change process. Which responsibility is the most important?


A.

Reviewing the change


B.

Discussing the change


C.

Analyzing the change


D.

Approving the change


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.