Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 264 Topic 27 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 264 Topic 27 Discussion

CAPM Exam Topic 27 Question 264 Discussion:
Question #: 264
Topic #: 27

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:


A.

exploit


B.

avoid


C.

mitigate


D.

share


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.