PMI Certified Associate in Project Management (CAPM) CAPM Question # 265 Topic 27 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 265 Topic 27 Discussion

CAPM Exam Topic 27 Question 265 Discussion:
Question #: 265
Topic #: 27

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:


A.

Adaptive


B.

Predictive


C.

Incremental


D.

Iterative


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.