Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 265 Topic 27 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 265 Topic 27 Discussion

CAPM Exam Topic 27 Question 265 Discussion:
Question #: 265
Topic #: 27

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?


A.

The risk of achieving the shortened project time is increased.


B.

The critical path will have positive total float.


C.

Contingency reserves are released for redeployment by the project manager.


D.

Duration buffers are added to maintain a focus on planned activity durations.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.