New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 263 Topic 27 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 263 Topic 27 Discussion

CAPM Exam Topic 27 Question 263 Discussion:
Question #: 263
Topic #: 27

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.

Which technique is the project manager using?


A.

Three-point estimating


B.

Parametric estimating


C.

Bottom-up estimating


D.

Data analysis


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.