Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 100 Topic 11 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 100 Topic 11 Discussion

CAPM Exam Topic 11 Question 100 Discussion:
Question #: 100
Topic #: 11

A project manager has just consolidated the project risk management plan and sent it to the sponsor. The sponsor wants to reduce the likelihood of a specific risk.

Which approach should the project manager take?


A.

Escalate


B.

Mitigate


C.

Avoid


D.

Transfer


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.