PMI Certified Associate in Project Management (CAPM) CAPM Question # 65 Topic 7 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 65 Topic 7 Discussion

CAPM Exam Topic 7 Question 65 Discussion:
Question #: 65
Topic #: 7

Which of the following is a project constraint?


A.

Twenty-five percent staff turnover is expected.


B.

The technology to be used is cutting-edge.


C.

Project leadership may change due to volatile political environment.


D.

The product is needed in 250 days.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.