Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 65 Topic 7 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 65 Topic 7 Discussion

CAPM Exam Topic 7 Question 65 Discussion:
Question #: 65
Topic #: 7

A project team working on an automobile manufacturing project is detailing the parts needed for a car door design. The door is composed of several parts that have to be developed in sequence, as the frame is needed before other parts can be designed and built. What activity is the team involved in?


A.

Creating a work breakdown structure (WBS)


B.

Identifying risks and issues in the project


C.

Developing a stakeholder engagement plan


D.

Developing a communications management plan


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.