PMI Certified Associate in Project Management (CAPM) CAPM Question # 41 Topic 5 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 41 Topic 5 Discussion

CAPM Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

Which type of risk diagram is useful for showing time ordering of events?


A.

Ishikawa


B.

Milestone


C.

Influence


D.

Decision tree


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.