CAPM Exam Topic 7 Question 69 Discussion:
Question #: 69
Topic #: 7

Which Project Time Management process includes bottom-up estimating as a tool or technique?


A.

Estimate Activity Resources


B.

Sequence Activities


C.

Estimate Activity Durations


D.

Develop Schedule