Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 72 Topic 8 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 72 Topic 8 Discussion

CAPM Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?


A.

US$S000


B.

US$9500


C.

US$10,000


D.

US$12,500


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.