CAPM Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

After an internal deliverable review session with the team, the project manager indicates some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and the required network. How would the project manager define extra costs?


A.

Appraisal costs


B.

Management reserves


C.

Cost of nonconformance


D.

Cost of conformance