PMI Certified Associate in Project Management (CAPM) CAPM Question # 128 Topic 13 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 128 Topic 13 Discussion

CAPM Exam Topic 13 Question 128 Discussion:
Question #: 128
Topic #: 13

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?


A.

Applying calendars


B.

Resource leveling


C.

Resource planning


D.

Resource conflict management


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.