Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 129 Topic 13 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 129 Topic 13 Discussion

CAPM Exam Topic 13 Question 129 Discussion:
Question #: 129
Topic #: 13

During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis.

What is this an example of?


A.

Monitoring the traceability matrix


B.

Managing the scope


C.

Maintaining the product backlog


D.

Managing the cost benefit


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.