PMI Certified Associate in Project Management (CAPM) CAPM Question # 157 Topic 16 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 157 Topic 16 Discussion

CAPM Exam Topic 16 Question 157 Discussion:
Question #: 157
Topic #: 16

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?


A.

Approved change requests


B.

Verified deliverables


C.

Lessons learned


D.

Work performance data


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.