PMI Certified Associate in Project Management (CAPM) CAPM Question # 157 Topic 16 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 157 Topic 16 Discussion

CAPM Exam Topic 16 Question 157 Discussion:
Question #: 157
Topic #: 16

The total of the planned value (PV) is also known as:


A.

work breakdown structure (WBS).


B.

schedule target.


C.

performance measurement baseline (PMB).


D.

earned value baseline.