PMI Certified Associate in Project Management (CAPM) CAPM Question # 109 Topic 11 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 109 Topic 11 Discussion

CAPM Exam Topic 11 Question 109 Discussion:
Question #: 109
Topic #: 11

An international company that is starting to practice an adaptive approach has several development teams located globally. They are having problems with multiple time zones and repetitive project schedule slippage. What effective tools should the project teams use to collaborate?


A.

Benchmark and adopt best practices that are being used by the competition.


B.

Focus on developing products by only using teams that are colocated.


C.

Arrange frequent colocated meetings and let the teams work together.


D.

Adopt an iterative development approach and conduct virtual meetings.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.