Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 109 Topic 11 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 109 Topic 11 Discussion

CAPM Exam Topic 11 Question 109 Discussion:
Question #: 109
Topic #: 11

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to evaluate the solution in the larger context to ensure it does not behave in unacceptable ways when deployed to production.

Which evaluation technique should be used here?


A.

Performance testing


B.

Integration testing


C.

Day-in-the-life testing


D.

Exploratory testing


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.