PMI Certified Associate in Project Management (CAPM) CAPM Question # 63 Topic 7 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 63 Topic 7 Discussion

CAPM Exam Topic 7 Question 63 Discussion:
Question #: 63
Topic #: 7

A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?


A.

Schedule the tasks in sequence.


B.

Increase quality review cycles.


C.

Expand the scope of the project.


D.

Schedule the tasks in parallel.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.