According to the PMBOK® Guide (Project Management Body of Knowledge), specifically within the Project Schedule Management knowledge area and the Sequence Activities process, project managers use leads and lags to refine the relationships between activities:
Lead (Option A): A lead is the amount of time a successor activity can be advanced with respect to a predecessor activity. In this scenario, " Painting " is the successor to " Preparing the walls. " Usually, these might have a Finish-to-Start (FS) relationship. However, if you can start the preparation while the paint is being chosen (essentially overlapping the tasks), you are accelerating the start of the successor. This overlap is a lead, often expressed as a negative value in scheduling software (e.g., FS - 2 days).
Lag (Option B): A lag is the amount of time a successor activity will be delayed with respect to a predecessor activity. An example of a lag in this context would be waiting 24 hours for the primer to dry before applying the final coat of paint. It is a required waiting time, not an overlap.
Mandatory Dependency (Option C): Also known as " hard logic, " this is a relationship inherent in the nature of the work (e.g., you cannot paint a wall that does not exist). Choosing paint and preparing walls are not physically dependent on each other in a way that requires one to be 100% finished before the other can begin.
Internal Dependency (Option D): This involves a precedence relationship between project activities that are generally within the project team ' s control. While this scenario is an internal dependency, the specific timing mechanism described (doing them at the same time to save time) is specifically defined as a lead.
In the PMI framework, using a lead is a technique often used during Schedule Compression (specifically Fast Tracking) to shorten the overall project duration by performing activities in parallel that would normally be done in sequence.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit