New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 25 Topic 3 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 25 Topic 3 Discussion

CAPM Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

Which of the following tools and techniques is used in the Verify Scope process?


A.

Inspection


B.

Variance analysis


C.

Expert judgment


D.

Decomposition


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.