Big 11.11 Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 57 Topic 6 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 57 Topic 6 Discussion

CAPM Exam Topic 6 Question 57 Discussion:
Question #: 57
Topic #: 6

The primary benefit of the Plan Schedule Management process is that it:


A.

provides guidance to identify time or schedule challenges within the project.


B.

tightly links processes to create a seamless project schedule.


C.

guides how the project schedule will be managed throughout the project.


D.

creates an overview of all activities broken down into manageable subsections.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.