CAPM Exam Topic 6 Question 54 Discussion:
Question #: 54
Topic #: 6

An input to the Manage Project Team process is:


A.

Work performance reports.


B.

Change requests.


C.

Activity resource requirements.


D.

Enterprise environmental factors.