Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 55 Topic 6 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 55 Topic 6 Discussion

CAPM Exam Topic 6 Question 55 Discussion:
Question #: 55
Topic #: 6

A team is working on a project using an adaptive approach. During project execution, the project gets delayed by one month due to an unforeseen risk. What should the team do next to deliver this project?


A.

Stop working on the project completely, even if the team can continue working on the tasks with the identified risk.


B.

Accept the project delay and add the risk to the lessons learned document for the next project.


C.

Change the delivery date and deliver the initially agreed-upon scope after mitigation of the identified risk.


D.

Reprioritize the work based on the increased visibility of the current risks.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.