PMI Certified Associate in Project Management (CAPM) CAPM Question # 394 Topic 40 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 394 Topic 40 Discussion

CAPM Exam Topic 40 Question 394 Discussion:
Question #: 394
Topic #: 40

An input of the Control Schedule process is the:


A.

resource calendar.


B.

activity list.


C.

risk management plan.


D.

organizational process assets.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.