Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 394 Topic 40 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 394 Topic 40 Discussion

CAPM Exam Topic 40 Question 394 Discussion:
Question #: 394
Topic #: 40

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?


A.

Reserve analysis


B.

Three-point estimating


C.

Parametric estimating


D.

Analogous estimating


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.