Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 102 Topic 11 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 102 Topic 11 Discussion

CAPM Exam Topic 11 Question 102 Discussion:
Question #: 102
Topic #: 11

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?


A.

Project sponsor


B.

Project manager


C.

Person responsible for project scheduling


D.

Person who is most familiar with the task


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.