CAPM Exam Topic 38 Question 376 Discussion:
Question #: 376
Topic #: 38

A procurement management plan is a subsidiary of which other type of plan?


A.

Resource plan


B.

Project management plan


C.

Cost control plan


D.

Expected monetary value plan