New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 376 Topic 38 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 376 Topic 38 Discussion

CAPM Exam Topic 38 Question 376 Discussion:
Question #: 376
Topic #: 38

What document gathers all of the lessons learned at the end of a phase or project


A.

Lessons learned register


B.

Lessons learned list


C.

Lessons learned project asset


D.

Lessons learned repository


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.