PMI Certified Associate in Project Management (CAPM) CAPM Question # 286 Topic 29 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 286 Topic 29 Discussion

CAPM Exam Topic 29 Question 286 Discussion:
Question #: 286
Topic #: 29

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?


A.

Close Project or Phase


B.

Conduct Procurements


C.

Control Procurements


D.

Close Procurements


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.