Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
The component of the risk management plan that documents how risk activities will be recorded is called:
Which tools or techniques are used during the Close Project or Phase process?
An example of a group decision-making technique is:
Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?
Stakeholder communication requirements should be included as a component of:
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
An input to the Perform Integrated Change Control process is:
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:
Through whom do project managers accomplish work?
Technical capability, past performance, and intellectual property rights are examples of:
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
Which action is included in the Control Costs process?
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?
Success is measured by benefits realization for a:
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?
Progressively elaborating high-level information into detailed plans is performed by the:
Which type of graphic is displayed below?

Whose approval may be required for change requests after change control board (CCB) approval?
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:
The following is a network diagram for a project.

What is the critical path for the project?
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?
Requirements documentation will typically contain at least:
Every project creates a unique product, service, or result that may be:
The zero duration of milestones in project planning occurs because milestones:
A project manager should communicate to stakeholders about resolved project issues by updating the:
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
Analytical techniques are a tool and technique of which process in Project Procurement Management?
In complex projects/ initiating processes should be completed:
Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?
A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?
Which items are components of a project management plan?
Which type of organizational structure is displayed in the diagram provided?

Which project document is updated in the Control Stakeholder Engagement process?
The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:
A reward can only be effective if it is:
Which tools or techniques are used in the Plan Schedule Management process?