Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 5 out of 8 pages
Viewing questions 201-250 out of questions
Questions # 201:

The following is a network diagram for a project.

Question # 201

The critical path for the project is how many days in duration?

Options:

A.

10


B.

12


C.

14


D.

17


Expert Solution
Questions # 202:

A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?

Options:

A.

Earned Schedule + Actual Time


B.

Actual Time - Earned Schedule


C.

Planned Value - Earned Value


D.

Earned Value - Planned Value


Expert Solution
Questions # 203:

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

Options:

A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.


B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.


C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.


D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.


Expert Solution
Questions # 204:

The initial development of a Project Scope Management plan uses which technique?

Options:

A.

Alternatives identification


B.

Scope decomposition


C.

Expert judgment


D.

Product analysis


Expert Solution
Questions # 205:

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

Options:

A.

Close Procurements.


B.

Control Procurements.


C.

Plan Procurements.


D.

Conduct Procurements.


Expert Solution
Questions # 206:

Recognition and rewards are tools and techniques of which process?

Options:

A.

Develop Team


B.

Manage Team


C.

Control Resources


D.

Plan Resource Management


Expert Solution
Questions # 207:

Which is an output from Distribute Information?

Options:

A.

Earned value analysis


B.

Trend analysis


C.

Project records


D.

Performance reviews


Expert Solution
Questions # 208:

Which type of graphic is displayed below?

Question # 208

Options:

A.

Work breakdown structure


B.

Context diagram


C.

Control chart


D.

Pareto diagram


Expert Solution
Questions # 209:

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Options:

A.

Finish-to-start planning


B.

Rolling wave planning


C.

Short term planning


D.

Dependency determination


Expert Solution
Questions # 210:

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

Options:

A.

Cost-reimbursable contracts


B.

Time and Material contracts (TandM)


C.

Fixed-price contracts


D.

Cost Plus Fixed Fee Contracts (CPFF)


Expert Solution
Questions # 211:

Which of the following includes how requirements activities will be planned, tracked, and reported?

Options:

A.

Configuration management plan


B.

Scope baseline


C.

Requirements management plan


D.

Schedule baseline


Expert Solution
Questions # 212:

The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?

Options:

A.

Project charter and stakeholder engagement plan


B.

Risk management plan and stakeholder engagement plan


C.

Communications management plan and stakeholder engagement plan


D.

Project charter and communications management plan


Expert Solution
Questions # 213:

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

Options:

A.

Organizational process assets


B.

A work breakdown structure


C.

The project management plan


D.

Enterprise environmental factors


Expert Solution
Questions # 214:

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

Options:

A.

Performing


B.

Storming


C.

Norming


D.

Forming


Expert Solution
Questions # 215:

When establishing a contingency reserve, including time, money and resources, how is the risk being handled?

Options:

A.

Accepting


B.

Transferring


C.

Avoiding


D.

Mitigating


Expert Solution
Questions # 216:

Which tasks should a project manager perform in order to manage the project schedule effectively?

Options:

A.

Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities. Develop Schedule


B.

Plan Schedule Management. Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule. Control Schedule


C.

Plan Schedule Management. Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of Activities. Develop Schedule


D.

Define Activities. Sequence Activities, Estimate Activity Durations. Define Quality of Activities. Estimate Cost of Activities, Develop Schedule


Expert Solution
Questions # 217:

Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

Options:

A.

Cause and effect diagram


B.

Control charts


C.

Pareto chart


D.

Histogram


Expert Solution
Questions # 218:

What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?

Options:

A.

Project Cost Management


B.

Project Integration Management


C.

Project Risk Management


D.

Project Schedule Management


Expert Solution
Questions # 219:

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).


B.

Cost Plus Fixed Fee Contract (CPFF).


C.

Fixed Price Incentive Fee Contract (FPIF).


D.

Time and Material Contract (TandM).


Expert Solution
Questions # 220:

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

Options:

A.

Checksheets


B.

Histograms


C.

Flowcharts


D.

Control charts


Expert Solution
Questions # 221:

Exhibit A is an example of which of the following types of Sequence Activities?

Options:

A.

Activity-on-arrow diagramming


B.

Precedence diagramming


C.

Project schedule network diagramming


D.

Mathematical analysis diagramming


Expert Solution
Questions # 222:

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

Options:

A.

Adaptive


B.

Predictive


C.

Incremental


D.

Iterative


Expert Solution
Questions # 223:

The chart below is an example of a:

Question # 223

Options:

A.

Responsibility assignment matrix (RAM)


B.

Work breakdown structure (WBS)


C.

RACI chart


D.

Requirements traceability matrix


Expert Solution
Questions # 224:

The following is a network diagram for a project.

The total float for the project is how many days?

Options:

A.

3


B.

5


C.

7


D.

9


Expert Solution
Questions # 225:

In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?

Options:

A.

Matrix - strong


B.

Matrix - balanced


C.

Virtual


D.

Functional


Expert Solution
Questions # 226:

In a weak matrix, the project managers role is:

Options:

A.

part-time


B.

full-time


C.

occasional


D.

unlimited


Expert Solution
Questions # 227:

What key component of the project charter defines the conditions for dosing a project phase?

Options:

A.

Purpose


B.

Approval requirements


C.

Exit criteria


D.

High-level requirements


Expert Solution
Questions # 228:

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

Options:

A.

Supportive


B.

Leading


C.

Neutral


D.

Resistant


Expert Solution
Questions # 229:

During a project ' s execution phase, the project manager reviews the communications management plan for communication technology factors. What can affect the choice of communications?

Options:

A.

Legal requirements


B.

Politics and power structures


C.

Internal information needs


D.

Sensitivity and confidentiality of the information


Expert Solution
Questions # 230:

Project reporting is a tool that is most closely associated with which process?

Options:

A.

Communicate Plan


B.

Manage Communications


C.

Report Performance


D.

Control Communications


Expert Solution
Questions # 231:

A product owner wants to ensure that the project ' s requirements, including product requirements, are met and validated. To do this project manager wants.

Match each process to its definition.

Question # 231


Expert Solution
Questions # 232:

What are the two most common contract types used in a project?

Options:

A.

Cost plus award fee (CPAF) contract and fixed price contract


B.

Fixed price contract and cost-reimbursable contract


C.

Cost-reimbursable contract and time and material (TandM) contract


D.

Time and material (TandM) contract and cost plus award fee (CPAF) contract


Expert Solution
Questions # 233:

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

Options:

A.

Negative


B.

Zero


C.

Positive


D.

Free


Expert Solution
Questions # 234:

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

Options:

A.

Portfolio


B.

Project


C.

Program


D.

Operations


Expert Solution
Questions # 235:

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

Options:

A.

quality audits


B.

process analysis


C.

statistical sampling


D.

benchmarking


Expert Solution
Questions # 236:

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

Options:

A.

Mitigate


B.

Transfer


C.

Share


D.

Avoid


Expert Solution
Questions # 237:

Project contracts generally fall into which of the following three broad categories?

Options:

A.

Fixed-price, cost reimbursable, time and materials


B.

Make-or-buy, margin analysis, fixed-price


C.

Time and materials, fixed-price, margin analysis


D.

Make-or-buy, lump-sum, cost-plus-incentive


Expert Solution
Questions # 238:

The milestone list is an input to which process from the Planning Process Group?

Options:

A.

Define Activities


B.

Estimate Activity Durations


C.

Estimate Activity Resources


D.

Sequence Activities


Expert Solution
Questions # 239:

While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.

What should the team do to ensure that this situation is managed?

Options:

A.

Implement Appropriate Response


B.

Plan Project Risk Management


C.

Perform Quantitative Risk Analysis


D.

Perform Qualitative Risk Analysis


Expert Solution
Questions # 240:

A method to manage stakeholder expectations in the scope statement is to clearly:

Options:

A.

state the guiding principles of the organization.


B.

identify alternatives to generate different approaches.


C.

state what is out of scope.


D.

outline the results of the Delphi technique.


Expert Solution
Questions # 241:

When cost variance is negative and schedule variance is positive, the project is:

Options:

A.

under budget and behind schedule.


B.

over budget and ahead of schedule.


C.

on schedule.


D.

complete; all planned values have been earned.


Expert Solution
Questions # 242:

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

Options:

A.

Issue log


B.

Change log


C.

Expert judgment


D.

Change requests


Expert Solution
Questions # 243:

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide


B.

The Standard for Program Management


C.

Organizational Project Management Maturity Model (OPM3$)


D.

Guide to the Project Management Body of Knowledge (PMBOK®)


Expert Solution
Questions # 244:

Which process is engaged when a project team member makes a change to project budget with project manager ' s approval

Options:

A.

Manage Cost Plan


B.

Estimate Costs


C.

Determine Budget


D.

Control Costs


Expert Solution
Questions # 245:

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

Options:

A.

Develop Project Team.


B.

Manage Project Team.


C.

Acquire Project Team.


D.

Plan Human Resource Management.


Expert Solution
Questions # 246:

Success is measured by benefits realization for a:

Options:

A.

strategic plan


B.

project


C.

portfolio


D.

program


Expert Solution
Questions # 247:

A quality management plan describes how the project and product scopes are managed in accordance with which of the following items?

Options:

A.

Product sponsor ' s expectation of organizational quality


B.

Historical quality standards and past organizational projects


C.

Organizational quality policies, stakeholder expectations, and historical data


D.

Organizational quality policies, standards, and methodologies


Expert Solution
Questions # 248:

A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?

Options:

A.

Identify the crashed project schedule to find the shortest duration to complete the project.


B.

Identify the longest activity path in the schedule with the shortest possible duration.


C.

Identify the tasks with float duration, which do not impact the duration of the project.


D.

Identify the path through the schedule with leveled resources and the shortest duration.


Expert Solution
Questions # 249:

Which of the following set of items belongs to the communications management plan?

Options:

A.

Escalation processes and meeting management


B.

Project schedule and glossary of common terminology


C.

Escalation processes and stakeholder communication requirements


D.

Interactive communication model and information to be communicated


Expert Solution
Questions # 250:

Who is responsible for initiating a project?

Options:

A.

Project sponsor


B.

Project manager


C.

Program manager


D.

Project management office (PMO)


Expert Solution
Viewing page 5 out of 8 pages
Viewing questions 201-250 out of questions