Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 5 out of 8 pages
Viewing questions 201-250 out of questions
Questions # 201:

A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements. What should the business analyst do?

Options:

A.

Prioritize requirements.


B.

Document requirements.


C.

Trace requirements.


D.

Validate requirements.


Expert Solution
Questions # 202:

Due to new market conditions a five-year project......need to be updated

Due to new market conditions a five-year project requires a full revision of project objectives. Which components to the stakeholder engagement plan need to be updated?

Options:

A.

Scope and impact of change to stakeholders


B.

Project scope and stakeholders goals


C.

Engagement level of key stakeholders


D.

Stakeholders expectations for the project


Expert Solution
Questions # 203:

In order to detect quality Issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches tor Project Quality Management?

Options:

A.

The frequency of the quality and review steps


B.

The number of deliverables


C.

The duration of each of the quality and review steps


D.

The tools used in the quality and review steps


Expert Solution
Questions # 204:

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

Options:

A.

mitigate


B.

accept


C.

transfer


D.

avoid


Expert Solution
Questions # 205:

After an internal deliverable review session with the team, the project manager indicates some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and the required network. How would the project manager define extra costs?

Options:

A.

Appraisal costs


B.

Management reserves


C.

Cost of nonconformance


D.

Cost of conformance


Expert Solution
Questions # 206:

An output of the Validate Scope process is:

Options:

A.

A requirements traceability matrix.


B.

The scope management plan.


C.

Work performance reports.


D.

Change requests.


Expert Solution
Questions # 207:

Howls program success measured?

Options:

A.

By delivering the benefit of managing the program ' s projects in a coordinated manner


B.

By the quality, timeliness, cost-etfectiveness. and customer saDstaction of the product or service


C.

By completing the right projects to achieve objectives rather than completing projects the right way


D.

By aggregating the successes of the individual projects in the program


Expert Solution
Questions # 208:

A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?

Options:

A.

Early requirements gathering


B.

Feedback analysis


C.

Progressive elaboration


D.

Requirements documentation


Expert Solution
Questions # 209:

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).


B.

Start-to-finish (SF).


C.

Finish-to-start (FS).


D.

Finish-to-finish (FF).


Expert Solution
Questions # 210:

A Project manager is using agile in a project. As development life cycle is adaptive, how does the project manager handle key stakeholder involvement?

Options:

A.

Key stakeholders are regularly involved


B.

Key stakeholders are continuously involved


C.

Key stakeholders are involved at specific milestones


D.

Key stakeholders are always involved


Expert Solution
Questions # 211:

What prototyping technique shows a sequence or navigations through a series of images or illustrations?

Options:

A.

Storyboarding


B.

Wireframes


C.

Data simulation


D.

Report prototyping


Expert Solution
Questions # 212:

Which of the in an adaptive project environment, which action helps the project manager?

Options:

A.

Project charter and project management plan


B.

Communications management plan and scope management plan


C.

Quality management plan and risk management plan


D.

Project scope statement and communications management plan


Expert Solution
Questions # 213:

How many Project Management Process Groups are there?

Options:

A.

3


B.

4


C.

5


D.

6


Expert Solution
Questions # 214:

Perform Quantitative Analysis focuses on:

Options:

A.

compiling a lsit of known risks and preparing responses to them


B.

assessing the probability of occurrence and impact for every risk in the risk register


C.

evaluating the contingency and management reserves required for the project


D.

analyzing numerically the impact of individual risks on the overall project ' s time and cost objectives


Expert Solution
Questions # 215:

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

Options:

A.

Initiating


B.

Monitoring and Controlling


C.

Planning


D.

Closing


Expert Solution
Questions # 216:

Which technique is used in Perform Quantitative Risk Analysis?

Options:

A.

Sensitivity analysis


B.

Probability and impact matrix


C.

Risk data quality assessment


D.

Risk categorization


Expert Solution
Questions # 217:

During the requirements verification process, stakeholders are finding many errors in the requirements definition. What could the business analyst have done to avoid these errors?

Options:

A.

Asked the stakeholders to write the requirements themselves


B.

Included the project manager in the elicitation sessions


C.

Confirmed the elicitation results after sessions


D.

Updated the requirements traceability matrix


Expert Solution
Questions # 218:

Which organizational process assets update is performed during the Close Procurements process?

Options:

A.

Procurement audit


B.

Lessons learned


C.

Performance reporting


D.

Payment requests


Expert Solution
Questions # 219:

A few project team members are having issues understanding the requirements as described. Which action should be taken to resolve this issue?

Options:

A.

Review the requirements traceability matrix and set up a meeting with the business analyst and key stakeholders.


B.

Review the requirements traceability matrix, the business analysis communications management plan, and set up a meeting with the business analyst and key stakeholders.


C.

Review the business analysis communications management plan and set up a meeting with the business analyst and key stakeholders.


D.

Review the project management plan and set up a meeting with the project manager and key stakeholders.


Expert Solution
Questions # 220:

A project manager who communicates to the project team though email is using which type of communication?

Options:

A.

Formal


B.

Informal


C.

Horizontal


D.

Unofficial


Expert Solution
Questions # 221:

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

Options:

A.

Escalate this issue to the project management office (PMO).


B.

Escalate this issue to the chief financial officer (CFO).


C.

Escalate this issue to the procurement team.


D.

Escalate this issue to the project sponsor.


Expert Solution
Questions # 222:

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Options:

A.

Work breakdown structure


B.

Organizational breakdown structure


C.

Resource breakdown structure


D.

Bill of materials


Expert Solution
Questions # 223:

The project manager is creating the communications management plan Which group of inputs Is required to begin?

Options:

A.

Work performance reports, change requests, and risk register


B.

Work performance data, project documents, and stakeholder engagement plan


C.

Project charter, project management plan, and project documents


D.

Work performance data, stakeholder register, and team management plan


Expert Solution
Questions # 224:

Which tool should a project manager use to calculate cost variance for a project?

Options:

A.

Contingency analysis


B.

Review lessons learned from similar projects


C.

Expert judgment


D.

Actual cost


Expert Solution
Questions # 225:

Which of the following is a goal of the project charter?

Options:

A.

Detail requirements for the project tasks.


B.

Empower the project manager to manage the project.


C.

List all tasks the team should perform in the project.


D.

Develop a business case to support the project.


Expert Solution
Questions # 226:

Which tools or techniques are used during the Close Project or Phase process?

Options:

A.

Reserve analysis and expert judgment


B.

Facilitation techniques and meetings


C.

Expert judgment and analytical techniques


D.

Performance reviews and meetings


Expert Solution
Questions # 227:

The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?

Options:

A.

Risk burnup and control chart


B.

Customer satisfaction index and workload


C.

Average burndown and velocity


D.

Average velocity and cycle time


Expert Solution
Questions # 228:

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

Options:

A.

Corrective action


B.

Defect repair


C.

Preventative action


D.

Probable action


Expert Solution
Questions # 229:

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

Options:

A.

Discussing with management


B.

Escalating to the sponsors


C.

Engaging regularly with stakeholders


D.

Engaging only with decision makers


Expert Solution
Questions # 230:

An input to the Control Quality process is:

Options:

A.

Activity attributes


B.

Quality control measurements


C.

Enterprise environmental factors


D.

Deliverables


Expert Solution
Questions # 231:

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

Options:

A.

Bottom-up


B.

Parametric


C.

Analogous


D.

Three-point


Expert Solution
Questions # 232:

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:

A.

Risk assessment analysis


B.

Make or buy analysis


C.

Contract value analysis


D.

Cost impact analysis


Expert Solution
Questions # 233:

In a project using agile methodology, who may perform the quality control activities?

Options:

A.

A group of quality experts at specific times during the project


B.

The project manager only


C.

All team members throughout the project life cycle


D.

Selected stakeholders at specific times during the project


Expert Solution
Questions # 234:

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

Options:

A.

Efficient


B.

Effective


C.

Push


D.

Pull


Expert Solution
Questions # 235:

Which of the following factors is lowest at the start of the project?

Options:

A.

Cost of changes


B.

Stakeholder influences


C.

Risk


D.

Uncertainty


Expert Solution
Questions # 236:

What are the Project Procurement Management processes?

Options:

A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements


B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements


C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements


D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements


Expert Solution
Questions # 237:

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

Options:

A.

Eleven weeks


B.

Nine weeks


C.

Eight weeks


D.

Ten weeks


Expert Solution
Questions # 238:

Which format can a network diagram take?

Options:

A.

Flow chart


B.

Control chart


C.

Affinity diagram


D.

Cause-and-effect diagram


Expert Solution
Questions # 239:

Which of the following is an input to the Direct and Manage Project Execution process?

Options:

A.

Approved change requests


B.

Approved contract documentation


C.

Work performance information


D.

Rejected change requests


Expert Solution
Questions # 240:

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Options:

A.

Project management plan.


B.

Project charter.


C.

Work breakdown structure.


D.

Stakeholder register.


Expert Solution
Questions # 241:

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning


B.

At the beginning and the end


C.

Once during each phase


D.

Repeatedly


Expert Solution
Questions # 242:

Which are the main objectives of Project Risk Management?

Options:

A.

Increase the probability of positive risks and decrease the probability of negative risks


B.

Avoid all kind of risks


C.

Increase the probability of positive risks and eliminate all negative risks


D.

Identify positive and negative risks


Expert Solution
Questions # 243:

When a dynamic systems development method (DSDM) practitioner receives a new high-priority feature request, what should the practitioner do first?

Options:

A.

Develop the feature as a parallel work package.


B.

Shorten the current work period and begin the new work.


C.

Ask a dedicated team member to complete it immediately.


D.

Prioritize it in the requirements list for the next work period.


Expert Solution
Questions # 244:

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.


B.

Control Procurements.


C.

Close Procurements.


D.

Conduct Procurements.


Expert Solution
Questions # 245:

Which tools and techniques will a project manager use to develop a project charter?

Options:

A.

Project manager experience, expert judgment, scope statement, and meetings


B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings


C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings


D.

Expert judgment, data gathering. interpersonal and team skills, and meetings


Expert Solution
Questions # 246:

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix


B.

Contingency analysis report


C.

Risk urgency assessment


D.

Rolling wave plan


Expert Solution
Questions # 247:

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

Options:

A.

Limited


B.

Low to moderate


C.

Moderate to high


D.

High to almost total


Expert Solution
Questions # 248:

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

Options:

A.

Work breakdown structure


B.

Requirements document


C.

Project charter


D.

Project management plan


Expert Solution
Questions # 249:

Which input to the Plan Risk Management process provides information on high-level risks?

Options:

A.

Project charter


B.

Enterprise environmental factors


C.

Stakeholder register


D.

Organizational process assets


Expert Solution
Questions # 250:

A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.

What should the project manager do first?

Options:

A.

Extend an iteration review invite to the new stakeholder.


B.

Perform qualitative risk analysis.


C.

Engage with the new stakeholder.


D.

Allow team members to share project status reports.


Expert Solution
Viewing page 5 out of 8 pages
Viewing questions 201-250 out of questions