PMI Certified Associate in Project Management (CAPM) CAPM Question # 234 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 234 Topic 24 Discussion

CAPM Exam Topic 24 Question 234 Discussion:
Question #: 234
Topic #: 24

A project manager should communicate to stakeholders about resolved project issues by updating the:


A.

project records


B.

project reports


C.

stakeholder notifications


D.

stakeholder register


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.