PMI Certified Associate in Project Management (CAPM) CAPM Question # 388 Topic 39 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 388 Topic 39 Discussion

CAPM Exam Topic 39 Question 388 Discussion:
Question #: 388
Topic #: 39

For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B and C are performed in parallel?


A.

3 days


B.

5 days


C.

7 daysD .10 days


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.