Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 233 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 233 Topic 24 Discussion

CAPM Exam Topic 24 Question 233 Discussion:
Question #: 233
Topic #: 24

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?


A.

Negative


B.

Zero


C.

Positive


D.

Free


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.