PMI Certified Associate in Project Management (CAPM) CAPM Question # 233 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 233 Topic 24 Discussion

CAPM Exam Topic 24 Question 233 Discussion:
Question #: 233
Topic #: 24

In a project, total float measures the:


A.

Ability to shuffle schedule activities to lessen the duration of the project.


B.

Amount of time an activity can be extended or delayed without altering the project finish date.


C.

Cost expended to restore order to the project schedule after crashing the schedule.


D.

Estimate of the total resources needed for the project after performing a forward pass.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.