PMI Certified Associate in Project Management (CAPM) CAPM Question # 233 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 233 Topic 24 Discussion

CAPM Exam Topic 24 Question 233 Discussion:
Question #: 233
Topic #: 24

The zero duration of milestones in project planning occurs because milestones:


A.

Are unpredictable and challenge the Plan Schedule Management process.


B.

Occur at random times in the project plans.


C.

Represent a moment in time such as a significant project point or event.


D.

Represent both significant and insignificant points in the project and are difficult to anticipate.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.