CAPM Exam Topic 39 Question 387 Discussion:
Question #: 387
Topic #: 39

What risk technique is used to quantify the probability and impact of risks on project objectives?


A.

Expert judgment


B.

Risk registry


C.

Risk response planning


D.

Interviewing