New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 160 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 160 Topic 17 Discussion

CAPM Exam Topic 17 Question 160 Discussion:
Question #: 160
Topic #: 17

In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?


A.

Add this risk to the lessons learned register on project completion.


B.

Add the stakeholder to the stakeholder register and add the risk to the risk register.


C.

Make sure proper testing gets completed to minimize the risk highlighted.


D.

Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.