PMI Certified Associate in Project Management (CAPM) CAPM Question # 136 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 136 Topic 14 Discussion

CAPM Exam Topic 14 Question 136 Discussion:
Question #: 136
Topic #: 14

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?


A.

Finish-to-start planning


B.

Rolling wave planning


C.

Short term planning


D.

Dependency determination


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.