Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 392 Topic 40 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 392 Topic 40 Discussion

CAPM Exam Topic 40 Question 392 Discussion:
Question #: 392
Topic #: 40

A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:


A.

To the project management plan.


B.

To the risk register.


C.

In the scope verification processes.


D.

And their impact to the project in terms of time, cost, and risk.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.