Question #: 213
Topic #: 22

Project Scope Management is primarily concerned with:


A.

Developing a detailed description of the project and product.


B.

Determining how requirements will be analyzed, documented, and managed.


C.

Defining and controlling what is and is not included in the project.


D.

Formalizing acceptance of the completed project deliverables.