CAPM Exam Topic 22 Question 213 Discussion:
Question #: 213
Topic #: 22

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?


A.

Influence/impact grid


B.

Power/influence grid


C.

Power/interest grid


D.

Salience model