Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 232 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 232 Topic 24 Discussion

CAPM Exam Topic 24 Question 232 Discussion:
Question #: 232
Topic #: 24

When should quality planning be performed?


A.

While developing the project charter


B.

In parallel with the other planning processes


C.

As part of a detailed risk analysis


D.

As a separate step from the other planning processes


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.