Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Certified Associate in Project Management (CAPM) CAPM Question # 231 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 231 Topic 24 Discussion

CAPM Exam Topic 24 Question 231 Discussion:
Question #: 231
Topic #: 24

In Project Cost Management, which input is exclusive to the Determine Budget process?


A.

Scope baseline


B.

Organizational process assets


C.

Project schedule


D.

Resource calendars


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.