PMI Certified Associate in Project Management (CAPM) CAPM Question # 231 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 231 Topic 24 Discussion

CAPM Exam Topic 24 Question 231 Discussion:
Question #: 231
Topic #: 24

When does the project team determine which dependencies are discretionary?


A.

Before the Define Activities process


B.

During the Define Activities process


C.

Before the Sequence Activities process


D.

During the Sequence Activities process


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.