Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 231 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 231 Topic 24 Discussion

CAPM Exam Topic 24 Question 231 Discussion:
Question #: 231
Topic #: 24

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?


A.

Bottom-up


B.

Parametric


C.

Analogous


D.

Three-point


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.