PMI Certified Associate in Project Management (CAPM) CAPM Question # 239 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 239 Topic 24 Discussion

CAPM Exam Topic 24 Question 239 Discussion:
Question #: 239
Topic #: 24

While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.

What should the team do to ensure that this situation is managed?


A.

Implement Appropriate Response


B.

Plan Project Risk Management


C.

Perform Quantitative Risk Analysis


D.

Perform Qualitative Risk Analysis