Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 240 Topic 25 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 240 Topic 25 Discussion

CAPM Exam Topic 25 Question 240 Discussion:
Question #: 240
Topic #: 25

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:


A.

Project management plan.


B.

Project charter.


C.

Work breakdown structure.


D.

Stakeholder register.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.