Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 238 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 238 Topic 24 Discussion

CAPM Exam Topic 24 Question 238 Discussion:
Question #: 238
Topic #: 24

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?


A.

0.50


B.

0.67


C.

1.50


D.

2.00


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.