PMI Certified Associate in Project Management (CAPM) CAPM Question # 238 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 238 Topic 24 Discussion

CAPM Exam Topic 24 Question 238 Discussion:
Question #: 238
Topic #: 24

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?


A.

Activity cost estimates


B.

Earned value management


C.

Cost management plan


D.

Cost baseline


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.