New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 238 Topic 24 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 238 Topic 24 Discussion

CAPM Exam Topic 24 Question 238 Discussion:
Question #: 238
Topic #: 24

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:


A.

Determine Budget.


B.

Baseline Budget.


C.

Control Costs.


D.

Estimate Costs.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.