New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 252 Topic 26 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 252 Topic 26 Discussion

CAPM Exam Topic 26 Question 252 Discussion:
Question #: 252
Topic #: 26

The project manager is creating the communications management plan Which group of inputs Is required to begin?


A.

Work performance reports, change requests, and risk register


B.

Work performance data, project documents, and stakeholder engagement plan


C.

Project charter, project management plan, and project documents


D.

Work performance data, stakeholder register, and team management plan


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.