Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 252 Topic 26 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 252 Topic 26 Discussion

CAPM Exam Topic 26 Question 252 Discussion:
Question #: 252
Topic #: 26

A project manager needs to determine the schedule variance (SV). The project manager ' s latest schedule indicates 14 units of work completed against a plan of 23 units.

What is the SV?


A.

-9


B.

37


C.

9


D.

322


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.