CAPM Exam Topic 25 Question 245 Discussion:
Question #: 245
Topic #: 25

Which tools and techniques will a project manager use to develop a project charter?


A.

Project manager experience, expert judgment, scope statement, and meetings


B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings


C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings


D.

Expert judgment, data gathering. interpersonal and team skills, and meetings