New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 244 Topic 25 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 244 Topic 25 Discussion

CAPM Exam Topic 25 Question 244 Discussion:
Question #: 244
Topic #: 25

Which of the following tasks focuses on decomposing work packages?


A.

Adjust duration estimates


B.

Define activities


C.

Complete rolling wave planning


D.

Develop milestone list


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.