PMI Certified Associate in Project Management (CAPM) CAPM Question # 243 Topic 25 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 243 Topic 25 Discussion

CAPM Exam Topic 25 Question 243 Discussion:
Question #: 243
Topic #: 25

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?


A.

Issue log


B.

Change log


C.

Expert judgment


D.

Change requests


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.