New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 205 Topic 21 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 205 Topic 21 Discussion

CAPM Exam Topic 21 Question 205 Discussion:
Question #: 205
Topic #: 21

The project scope statement and resource calendars are inputs to which Project Time Management process?


A.

Sequence Activities


B.

Estimate Activity Resources


C.

Develop Schedule


D.

Control Schedule


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.